Marine Licence - Alternative Landfall Cable Installation Method - Seagreen Alpha and Bravo Wind Farm Area, Firth of Forth – 07050/00009445/00009749/00010440/00010567

The alternative methodology is for ploughing or mechanical trenching (also termed ‘open cut’ trenching), which is being considered in addition to the already consented Horizontal Directional Drilling installation methodology consented under the existing offshore transmission asset marine licence (04678/19/0). 

Application reference number: 
00010567
Licence ID: 
00010028
Application type: 
Construction, alteration or improvement of any works
Application stage: 
Application
Applicant name: 
Seagreen Wind Energy Limited
Applicant address: 
No 1 Forbury Place
43 Forbury Road
Reading
RG1 3JH
United Kingdom
Licence holder: 
Seagreen Wind Energy Limited
Date of application: 
2023-09-29
Date licence granted: 
2022-09-29
Licence commencement date (as granted): 
2022-09-30
Licence expiry date (as granted): 
2023-06-30

This application is part of the following projects:

MS-LOT Associated application docs