Section 36 Consent Variation - Construction and Operation of Offshore Windfarm and Transmission Works - Inch Cape Offshore Windfarm (Revised Design), Firth of Forth
Section 36 consent granted on 17 June 2019 to Inch Cape Offshore Limited ("ICOL") for the construction, operation and maintenance of the Inch Cape Offshore Wind Farm, approximately 15-22km east off Angus coastline.
On 30 January 2020, ICOL submitted an application to the Scottish Ministers for a variation to the existing Section 36 Consent seeking to increase the generating capacity from around 700MW to up to 1000MW without changing any of the physical parameters of the turbines.
Application reference number:
048/OW/RRP – 10
Application type:
Renewables - Wind
Application stage:
Licence
Applicant name:
Inch Cape Offshore Limited
Applicant address:
5th Floor, 40 Princes Street
Edinburgh
EH2 2BY
Date of application:
2020-01-30
Date licence granted:
2020-07-16